ICRC Services
ICRC superintends and regulates PPPs in Nigeria
The ICRC through the PPP Resource Department has a responsibility to provide guidance to MDAs to ensure PPP projects are developed within the approved regulatory, institutional and legal framework.
This involves:
- Developing and disseminating policies, procedures and guidelines on best practices for effectively engaging private sector participation in PPPs.
- Providing pre-contract regulation and guidelines for project origination, identification, appraisal, design, procurement and implementation.
- Maintaining the national PPP project database,
- Coordinating PPP activities across the Federation,
- Managing flow of projects to the market
- Assisting States to set up PPP legal and regulatory environment.
- Acting as a centre of technical expertise for MDAs/States
Another major part of ICRC’s pre-regulatory functions includes revising the Outline Business Case (OBC) and Full Business Case (FBC) for every PPP project and granting a certificate of compliance on each occasion to the MDA. This certificate is required before approval can be sought from FEC.
OUTLINE BUSINESS CASE
The purpose of the Outline Business Case (OBC) is to seek approval from the government for the preferred project and procurement options and to obtain funding if the project is not financially free standing. It also contains justifications for the preferred project and procurement options. It provides information regarding the expected value for money of the preferred project and procurement options. A typical OBC consists of the following sections:
- Executive Summary
- A summary of the key conclusions and recommendations arising from developing the appraisal process, and an analysis of the next steps required for taking forward the project;
- A statement of the support and commitment of the public sector client (and other key stakeholders);
- An analysis of the strategic context in which the service is provided, the business need for the service (including details of the contribution that the service should make to the department’s corporate strategy) and the synergies that exist between the service and the public sector client’s corporate objectives;
- An overview of the existing services provided, including analysis of existing service strengths and weaknesses, key service standards, outputs, the condition of the current assets or infrastructure, and trends in public opinion about the service;
- A summary of the public sector client’s objectives for the service, as used in conducting the appraisal of project and procurement options (and subsequently to be used throughout the procurement process);
- A brief description of the options appraisal process that was followed in order to identify the preferred project and procurement option (including a summary of the financial and non-financial outcomes).
- An assessment of the economic benefits, value for money, affordability, and bankability of the preferred service delivery option. This should include confirmation that the private organizations expressed their interest in the preferred service delivery option.
- An overview of the public sector client’s approach to developing and delivering the project, including consideration of contractual terms, the balance sheet treatment, and project management arrangements.
- Strategic Context and Business Need
- How the public perceptions have developed over time;
- How they reflect demand for better quality or more efficient services, any public and community opinion surveys on trends in relation to the performance of the service;
- The results of any consultation process in relation to the service;
- Analysis of the numbers and frequency of requests for service and/or complaints;
- Analysis of the requests for improvements to the service; and
- The results of other surveys/initiatives where improvements to the service have been cited as a means of improving the efficiencies of other department’s activities.
- The current service fails to maximize its contribution to the public sector client’s strategies;
- The services delivered by the project can contribute to the broader strategies of the public sector client;
- The project forms a logical and coherent part of the public sector client’s strategies and plans; and
- There is a fit of the project within the wider strategic and policy context.
- Service or Project Objectives
- Preferred Project Option and Procurement Option
- Comparison between the cost of delivering the preferred project option through traditional procurement method, the Public Sector Comparator (PSC), compared to that delivered through private delivery option, the Private Finance Project (PFP);
- To demonstrate that the private parties have the capability to deliver the required services, within any constraints set by the public sector client, the service delivery would be sufficiently reliable, and that such delivery would provide value for money;
- To justify that the risks and rewards inherent in providing the required outputs represent a genuine commercial opportunity;
- To confirm that the finance market at the time will support the proposal; and
- To illustrate that there are opportunities for cost-effective risk transfer.
- Project Delivery Arrangements
- Output Specification:The OBC should include a summary of the key elements of the draft output specification and commentary on how the output specification will be developed further.
- Proposed Performance Measurement and Payment Mechanism: The OBC should identify the key performance indicators which will measure performance and the key components of the payment mechanism. Discussions should cover the relationship between payments from the public sector client and the related necessary level of performance.
- Indexation, Benchmarking and Market Testing:The OBC should set out the public sector client’s initial views on indexation, benchmarking and market testing, which will be included as part of the payment mechanism and contract for the services.
- Contractual Terms:The OBC should set out how the public sector client will develop the contract for the project. It should indicate how the public sector client expects to deal with the key contractual issues associated with the particular type of project.
- Risk:The OBC should identify all material risks associated with the project, specifying the external and project development risks for the public sector client, the project risks to be allocated to a private party, and those to be retained by the public sector client. It should also include any project transition risk, such as interest rate or planning risks that may be carried by the public sector client until allocated to the private party when contracts are operating. This is a key area of the business case, as optimal risk allocation is a fundamental driver of value for money. For risks that are proposed to be retained by the public sector client, the business case needs to explain why the public sector client is considered better able to manage or mitigate these risks. The business case should include at least a preliminary view on the cost to the public sector client of the risks which are to be built into the Public Sector Comparator (PSC).
- Implementation and Project Management Plan:The outline business case should document the public sector client’s approach to the development of the project management arrangements if the project secures approval to go into procurement, and describe the arrangements that are in place, or to be put in place, to ensure an efficient procurement. It should identify the members of the project team, the delegations and reporting arrangements that have been agreed for the procurement stage, and the arrangements for involving stakeholders in the procurement process. The OBC should also set out the approval process required for the OBC, details of the commitment of members to funding the project, and evidence of the support of key stakeholders.
- Project Timetable and Resourcing:An indicative project timetable should show each of the key stages such as the procurement stage, construction stage, and delivery of service in the whole process and the estimated time for service delivery to begin. Regarding the procurement timetable, indicative periods for each sub-stage, such as invitation to expression of interests in the procurement process should be given. The procurement timetable will need to be updated as the procurement proceeds and should serve both as a project management tool and as a means of communication. The discussion should also deal with the resources required to deliver the project, how they will be secured – internally or externally, and the expected costs of the procurement team.
THE FULL BUSINESS CASE
Before awarding the contract to the preferred tenderer, there is the need to seek approval from the government. A Full Business Case (FBC) is prepared for seeking approval prior to subsequent award of contract.
The Full Business Case should:
- report on the conclusions of the Request for Proposal and set out the full scope and cost of the project;
- be a supporting document to a public sector client’s submission once a preferred tenderer has been selected;
- include a qualitative assessment of the preferred tenderer and a Full Public Sector Comparator (PSC) comparison against the preferred tender to conform that best value for money is achievable; and
- provide government with an indication of the public sector client’s forward plan for proceeding with the project and finalizing a contract with the preferred tenderer.
- Executive Summary
- The service provider
- Term of the contract
- The expected investment regime included in the contract
- The estimated economic benefits and non-economic benefits of the project
- The fit of the project with other public sector client’s policies and strategies
- The quality of the service delivery arrangements and negotiated design against that envisaged in the OBC
- A summary of the performance standards and performance targets agreed with the service provider, including where appropriate, how these fit with any statutory targets.
- Project Objectives
- Financial Issues and Affordability
- Value for money:an estimate of the value of money savings anticipated from procuring the service through a Private Finance Initiative (PFI) arrangement would have been included in the OBC. This should be updated with out-turn costs of the PFI scheme. In addition, if there have been material changes to the assumptions used in determining the Public Sector Comparator (PSC) at the OBC stage, appropriate commentary should be included on these and an updated PSC calculated and included in the FBC.
- Affordability:The public sector client will have made an assessment of the affordability of the project at the OBC stage. This computation should be updated using out-turn figures for the negotiated PFI contract. Commentary should be included on how any material changes since the OBC was prepared are to be dealt with.
- Stakeholder Consultation
- Internal stakeholders:Outlining how the project has been developed by the procurement broad, in consultation with members, the strategic/stakeholder board, relevant departments and other internal stakeholders.
- Community and Staff:outlining how the local community and relevant staff have been consulted throughout the process.
- Procurement Process and Competition
- The Invitation to Expression of Interest
- Pre-qualification and short-listing
- Evaluation of Request for Proposal
- Selection of Preferred Tenderer
- Negotiations to financial close
- Risk allocation and accounting treatment
- Contract and Payment Mechanisms
- The position agreed on the treatment of taxation
- The anticipated third party revenues included or anticipated in the Contract
- The proposals included in the Contract as regards any revenue sharing arrangements
- Any proposals for benchmarking and market testing.