FEDERAL EXECUTIVE COUNCIL APPROVED PPP PROJECTS – 2010 - 2023 | ||||||
S/N | Project Name & Description / Current Status
| MDA / Grantor
| FEC Approval Date/Duration of Concession | Concessionaire
| Status | Value of Concession / Project cost |
1 | Provision of Engineering Infrastructure for Katampe District, FCT
Design, Finance, Build and Transfer of Engineering Infrastructure for Katampe District
PPP Process: Solicited
| Federal Capital Development Authority (FCDA) | FEC Approval: May, 2010
Duration: 8 years | Deanshanger Project Limited
| On Hold. Ministry reviewing the structure of the Project. | NGN 61,194,747,645 |
2 | Lekki Deep Sea Port
The Development and Operation of a Deepwater Port in the Lagos Free Trade Zone at Ijebu Lekki, Lagos State
PPP Process: Solicited
| Federal Ministry of Transportation / Nigeria Ports Authority | FEC Approval: April, 2011
Duration: 45 years | Lekki Port LFTZ Enterprises | At Implementation Phase | NGN 504,000,000,000 |
3 | Security, Monitoring and Enforcement Concession
Effective enhancement of security of ships and ports to minimise the incidents of piracy and armed robbery at sea.
PPP Process: Restricted Bidding (Sole Source) with Security Clearance by ONSA
| Nigerian Maritime Administration and Safety Agency (NIMASA) | 3rd April 2012
Duration: 10years | Global West Vessel Specialist Nigeria Limited | On hold. | NGN 37,224,000,000 |
4 | Kainji/Jebba Hydro Electric Power Plants
Concession of the Kainji/Jebba Hydro Electric Power Plants to improve national power generation
PPP Process: Solicited
| BPE/Federal Ministry of Power | February, 2013
Duration: 30 years | Mainstream Energy Solutions Limited
| Project at Implementation Phase | NGN 114,690,823,560 |
5 | Shiroro Hydro Electric Power Plant
Concession of the Shiroro Hydro Electric Power Plant to improve national power generation
PPP Process: Solicited
| BPE / Federal Ministry of Power | February, 2013
Duration: 30 years | North South Power Company Limited
| Under implementation | NGN 48,692,526,480 |
6 | Phase 4B Port Facilities at Onne Oil and Gas Free-Zone
The Development of Phase 4B Port Facilities at Onne Oil and Gas Free-Zone
PPP Process: Unsolicited
| Federal Ministry of Transportation (FMoT) | 17 May, 2013 | Deep Offshore Services Nigeria Ltd | Under implementation | NGN 1,020,952,173,789.90 |
7 | Berth 21 at Apapa Terminal E The concession of Berth 21 at Apapa Port, Lagos
PPP Process: Solicited
| Federal Ministry of Transportation (FMoT) | 28 Mar, 2014 | Green View Limited | Under implementation | NGN 41,506, 944,577 |
8 | Development of FESTAC Phase 2 Housing Estate, Lagos
Concession for the Reclamation and infrastructural Development of the land at FESTAC Phase 2 Estate, Lagos
PPP Process: Solicited
| Federal Ministry of Lands, Housing & Urban Development / Federal Housing Authority | 8 Sep, 2014
Duration: 30 years | New FESTAC Property Development Company Ltd | Yet to commence due to Court cases with Amuwo Odofin Community Chiefs | NGN 18,983,650,000 |
9 | Debt Management Office (DMO) Complex
Development of office complex involving the design, finance, build, operate, maintain and transfer of the building; and receive rents and service charges derived from the lease of 15 floors of the first tower and all 20 floors of the second tower
PPP Process: Unsolicited
| Debt Management Office | FEC Approval: 13 May, 2015
Duration: 30 years | LOH & OR Construction Company Limited | Project yet to achieve Financial Close | NGN 41,506, 944,577 |
10 | Trans-Nigeria Gas Pipeline: AKK Project
The construction of 614km gas pipeline from Ajaokuta to Kano (AKK) with off take Gas Stations in Abuja, Kaduna and Kano.
PPP Process: Solicited
| Federal Ministry of Petroleum / Nigeria National Petroleum Corporation (NNPC) | FEC approval: 13 Dec, 2017
| Lot 1: Oando/OilServe consortium
Lot 3: China Petroleum Pipeline (CPP)/Brentex consortium | Contracts for Lot 1 and Lot 3 were signed in April 2018 while that of Lot 2 was not executed. Lot 2 was shared to Lots 1 and 3, which became Segments 1 and 2. These are being negotiated by the EPC Contractors, the Chinese financial institutions and the NNPC for financial close | NGN 1,022,000,000,000.00 |
11 | Hydroelectric power at existing Small & Medium Dams across the Country
The development of Hydroelectric power from existing 6 Small & Medium from dams across the Country Federal Executive Council (FEC) gave an approval on the 30th November 2016 for 6 dams. Dam 1 -Bakolori Dam, Zamfara State
PPP Process: Solicited
| Federal Ministry of Power, Works & Housing (Power) | FEC approval:
Duration: 30 years March 27, 2018 | Pan-African Global Infrastructure Company Ltd
| Yet to achieve commercial close | NGN 1,553,167,000.0
|
12 | Hydroelectric power at existing Small & Medium dams across the Country
Development of Hydroelectric power from existing 6 Small & Medium from dams across the Country Federal Executive Council (FEC) gave an approval on the 30th November 2016 for 6 dams. Dam 2 - Omi - Kampe Dam, Kogi State
PPP Process: Solicited
| Federal Ministry of Power, Works & Housing (Power) | FEC approval:
Duration: 30 years March 27, 2018 | Messrs Quaint Power Infrastructure Nigeria Ltd/Engie
| Yet to achieve commercial close | NGN 1,212,452,500 |
13 | Hydroelectric power at existing Small & Medium dams across the Country
Development of Hydroelectric power from existing 6 Small & Medium from dams across the Country Federal Executive Council (FEC) gave an approval on the 30th November 2016 for 6 dams. Dam 3 - Ikere Gorge Dam, Oyo State
PPP Process: Unsolicited (Swiss challenge)
| Federal Ministry of Power, Works & Housing (Power) | FEC approval:
Duration: 30 years March 27, 2018 | Messrs Power Control & Appliances Ltd | Preferred bidder declined the award. Reserve bidder (Messrs Quaint Power Infrastructure Nigeria Ltd/Engie) now onboard. FBC under review. | NGN 3,650,000,000.0 |
14 | Hydroelectric power at existing Small & Medium dams across the Country
Development of Hydroelectric power from existing 6 Small & Medium from dams across the Country Federal Executive Council (FEC) gave an approval on the 30th November 2016 for 6 dams. Dam 4 - Jibiya Dam, Katsina State
PPP Process: Solicited
| Federal Ministry of Power, Works & Housing (Power) | FEC approval:
Duration: 30 years March 27, 2018 | Pan-African Global Infrastructure Company Ltd
|
Yet to achieve commercial close | NGN 1,315,470,000.0 |
15 | Hydroelectric power at existing Small & Medium dams across the Country
Development of Hydroelectric power from existing 6 Small & Medium from dams across the Country Federal Executive Council (FEC) gave an approval on the 30th November 2016 for 6 dams. Dam 6- Zobe Dam, Katsina State
PPP Process: Solicited
| Federal Ministry of Power, Works & Housing (Power) | FEC approval:
Duration: 30 years March 27, 2018 | Pan-African Global Infrastructure Company Ltd
| Yet to achieve commercial close | NGN 434,630,000.0 |
16 | Warehouse in a Box– Abuja and Lagos Provision of physical infrastructure – an insulated warehouse, made up of pre-engineered modular components (prefabricated insulated expanded polystyrene sandwiched panels) – as well as the fittings and operating components, including offices, furnishings, racking, kitting, security and office equipment.
PPP Process: Solicited | Federal Ministry of Health | FEC Approval: 28 Nov, 2018
Duration: 5 years | MDS Logistics Ltd | Under implementation | NGN 668,880,000.0 |
17 | Roof Top Solar Powered Project, Power House
Design, Build, Finance, Operate a 750kw Day Time and 75kw Night Time Hybrid Solar Power Facility in a PPP arrangement at the Power House, Maitama, Abuja
PPP Process: Solicited
| Federal Ministry of Power, Works and Housing (Power Sector) | FEC Approval: 13 Sep, 2018
Duration: 10 years | Proserve Energy Services Ltd | Yet to achieve financial close | NGN 690,079,950.0 (Equipment Only) |
18 | Concession of Grain Storage Facility, Ado Ekiti, Ekiti State
Operations and Management of grain silo complexes in Nigeria
PPP Process: Solicited
| Federal Ministry of Agriculture and Rural Development (FMARD) | FEC Approval: 19 Sep, 2018
Duration: 10 years | Agro Universal Consortium | Under implementation | NGN 485,767,625.0 |
19 | Concession of Grain Storage Facility, Akure, Ondo State
Operations and Management of grain silo complexes in Nigeria
PPP Process: Solicited
| Federal Ministry of Agriculture and Rural Development (FMARD) | FEC Approval: 19 Sep, 2018
Duration: 10 years | Agro Universal Consortium | Under implementation | NGN 105,775,991.0 |
20 | Concession of Grain Storage Facility, Bauchi, Bauchi State
Operations and Management of grain silo complexes in Nigeria
PPP Process: Solicited
| Federal Ministry of Agriculture and Rural Development (FMARD) | FEC Approval: 19 Sep, 2018
Duration: 10 years | Agro Universal Consortium | Under implementation | NGN 128,663,089.0 |
21 | Concession of Grain Storage Facility, Bulasa, Zamfara State
Operations and Management of grain silo complexes in Nigeria
PPP Process: Solicited
| Federal Ministry of Agriculture and Rural Development (FMARD) | FEC Approval: 19 Sep, 2018
Duration: 10 years | Matrixville Consortium | Under implementation | NGN 2,073,800,654.0 |
22 | Concession of Grain Storage Facility, Ezillo, Ebonyi State
Operations and Management of grain silo complexes in Nigeria
PPP Process: Solicited
| Federal Ministry of Agriculture and Rural Development (FMARD) | FEC Approval: 19 Sep, 2018
Duration: 10 years | Ebony Agro Industries Limited |
Under implementation | NGN 1,893,793,273.0 |
23 | Concession of Grain Storage Facility, Gaya, Kano State
Operations and Management of grain silo complexes in Nigeria
PPP Process: Solicited
| Federal Ministry of Agriculture and Rural Development (FMARD) | FEC Approval: 19 Sep, 2018
Duration: 10 years | Agro Universal Consortium | Under implementation | NGN 236,930,364.0 |
24
| Concession of Grain Storage Facility, Gombe, Gombe State
Operations and Management of grain silo complexes in Nigeria
PPP Process: Solicited
| Federal Ministry of Agriculture and Rural Development (FMARD) | FEC Approval: 19 Sep, 2018
Duration: 10 years | Servewell Agricultural Service Limited | Under implementation | NGN 429,426,464.0 |
25 | Concession of Grain Storage Facility, Ibadan, Oyo State
Operations and Management of grain silo complexes in Nigeria
PPP Process: Solicited
| Federal Ministry of Agriculture and Rural Development (FMARD) | FEC Approval: 19 Sep, 2018
Duration: 10 years | Independent Grain Handling and Storage Limited | Under implementation | NGN 575,912,947.0 |
26 | Concession of Grain Storage Facility, Igbariam, Anambra State
Operations and Management of grain silo complexes in Nigeria
PPP Process: Solicited
| Federal Ministry of Agriculture and Rural Development (FMARD) | FEC Approval: 19 Sep, 2018
Duration: 10 years | Coscharis Farms Limited | Under implementation | NGN 254,241,286.0 |
27 | Concession of Grain Storage Facility, Ikenne, Ogun State
Operations and Management of grain silo complexes in Nigeria
PPP Process: Solicited
| Federal Ministry of Agriculture and Rural Development (FMARD) | FEC Approval: 19 Sep, 2018
Duration: 10 years | Agro Universal Consortium | Under implementation | NGN 626,505,802.0 |
28 | Concession of Grain Storage Facility, Jahun, Jigawa State
Operations and Management of grain silo complexes in Nigeria
PPP Process: Solicited
| Federal Ministry of Agriculture and Rural Development (FMARD) | FEC Approval: 19 Sep, 2018
Duration: 10 years | Matrixville Consortium | Under implementation | NGN 487,677,696.0 |
29 | Concession of Grain Storage Facility, Jos, Plateau State
Operations and Management of grain silo complexes in Nigeria
PPP Process: Solicited
| Federal Ministry of Agriculture and Rural Development (FMARD) | FEC Approval: 19 Sep, 2018
Duration: 10 years | Agro Universal Consortium | Under implementation | NGN 176,688,747.0 |
30 | Concession of Grain Storage Facility, Kaduna, Kaduna State
Operations and Management of grain silo complexes in Nigeria
PPP Process: Solicited
| Federal Ministry of Agriculture and Rural Development (FMARD) | FEC Approval: 19 Sep, 2018
Duration: 10 years | Matrixville Consortium | Under implementation | NGN 541,806,691.0 |
31 | Concession of Grain Storage Facility, Kwali, Abuja, FCT
Operations and Management of grain silo complexes in Nigeria
PPP Process: Solicited
| Federal Ministry of Agriculture and Rural Development (FMARD) | FEC Approval: 19 Sep, 2018
Duration: 10 years | Matrixville Consortium | Under implementation | NGN 2,246,942,955.0 |
32 | Concession of Grain Storage Facility, Lafiagi, Kwara State
Operations and Management of grain silo complexes in Nigeria
PPP Process: Solicited
| Federal Ministry of Agriculture and Rural Development (FMARD) | FEC Approval: 19 Sep, 2018
Duration: 10 years | Matrixville Consortium | Under implementation | NGN 227,649,132.0 |
33 | Concession of Grain Storage Facility, Makurdi, Benue State
Operations and Management of grain silo complexes in Nigeria
PPP Process: Solicited
| Federal Ministry of Agriculture and Rural Development (FMARD) | FEC Approval: 19 Sep, 2018
Duration: 10 years | Upland Grains Production Company Limited | Under implementation | NGN 442,382,759.0 |
34 | Concession of Grain Storage Facility, Minna, Niger State
Operations and Management of grain silo complexes in Nigeria
PPP Process: Solicited
| Federal Ministry of Agriculture and Rural Development (FMARD) | FEC Approval: 19 Sep, 2018
Duration: 10 years | Niger Resources Limited | Under implementation | NGN 3,759,277,152.0 |
35 | Concession of Grain Storage Facility, Ogoja, Cross River State
Operations and Management of grain silo complexes in Nigeria
PPP Process: Solicited
| Federal Ministry of Agriculture and Rural Development (FMARD) | FEC Approval: 19 Sep, 2018
Duration: 10 years | Agro Universal Consortium | Under implementation | NGN 27,613,845.0 |
36 | Concession of Grain Storage Facility, Sokoto, Sokoto State
Operations and Management of grain silo complexes in Nigeria
PPP Process: Solicited
| Federal Ministry of Agriculture and Rural Development (FMARD) | FEC Approval: 19 Sep, 2018
Duration: 10 years | Agro Universal Consortium | Under implementation | NGN 196,719,866.0 |
37 | Concession of Grain Storage Facility, Uyo, Akwa Ibom State
Operations and Management of grain silo complexes in Nigeria
PPP Process: Solicited
| Federal Ministry of Agriculture and Rural Development (FMARD) | FEC Approval: 19 Sep, 2018
Duration: 10 years | Neon Farms Africa Consortium | Under implementation | NGN 182,163,107.0 |
38 | ECOWAS Biometric ID Cards System
This project involves the adoption of smart card and biometric technology to secure the identification of documents as a prerequisite for managing migration and to enhance regional security, which is the outcome of the deliberation of ECOWAS Heads of Governments in order to meet the challenges posed by migration.
PPP Process: Unsolicited
| Federal Ministry of Interior | FEC Approval: 28 Nov, 2018
Duration: 10 Years | Euphoria Press Limited | Contract executed | NGN 14,700,000,000.0 |
39 | Development of Abuja-Warri Railway Line with Branch Line and Extensions from Jakura-Lokoja and Agbarho-Warri (ii) Warri New Sea Port
i. Abuja-Baro-Itakpe-Ajaokuta-Warri Railway Line (269.12km) with branch and extension lines to Jakura-Lokoja (41km) and Agbarho-Warri (5km)
The project is a Design-Build-Operate and Transfer (DBOT) designed to promote passenger and freight services, promote regional infrastructure development, preserve the life span of roads, encourage inter-model transport system, job creation and promote economic recovery and growth plans of the Federal Government, etc.
PPP Process: Solicited
| Federal Ministry of Transportation | FEC Approval: November, 2018 | Messrs. China Railway Construction Company International (CRCC(I)) | Ministry currently reviewing the terms of the project | NGN3.199 billion |
40 | Development of Abuja-Warri Railway Line with Branch Line and Extensions from Jakura-Lokoja and Agbarho-Warri (ii) Warri New Sea Port
ii. Development of Warri new Seaport, Warri, Delta State
The project is a Design-Build-Operate and Transfer (DBOT) designed to promote passenger and freight services, promote regional infrastructure development, preserve the life span of roads, encourage inter-model transport system, job creation and promote economic recovery and growth plans of the Federal Government, etc.
PPP Process: Solicited
| Federal Ministry of Transportation | FEC Approval: November, 2018 | Messrs. China Railway Construction Company International (CRCC(I)) | Ministry currently reviewing the terms of the project | N880.089 million |
41 | Concession of the Power Components of Gurara 1 30MW Dam
This is for the O & M of the dam, as the FMoWR has completed the construction of this facility and its multi-purpose assets.
PPP Process: Solicited
| Federal Ministry of Water Resources | FEC Approval: May 19, 2019 | North South Power ltd | Project delay due to non-completion of transmission line | NGN 6,679,288,975.0
|
42 | Development of Small & Medium Enterprise (SME) Portal Project
A technology enabled platform project that will encourage more MSMEs to be attracted into the formal sector
PPP Process: Solicited
| Federal Ministry of Industry Trade and Investment | FEC Approval: May 19, 2019 | Venture Garden Group / PWC | On hold. A similar project submitted by the Ministry | |
43 | Gurara Facility Management
The project involves procurement of a Facility Manager to manage, operate and maintain all infrastructure facilities and services in Gurara dam.
PPP Process: Solicited
| Federal Ministry of Water Resources | FEC Approval: May 19, 2019 | Gams and Abel / RYZYN Global INC. JV USA | Under implementation | |
44 | Establishment of Military & Paramilitary Clothing & Accessories Factory at DICON, Kaduna State
i. Establishment of selected weapons and military equipment assembly lines Powered Generating set
PPP Process: Solicited
| Federal Ministry of Defence | FEC Approval: 12th July, 2019 | Sur Corporate Wear | Under implementation | US$13 million |
45 | Automated Customs Gateway Portal for Import Duty Exemption Certificate (IDEC) and Imported Vehicle Identification Number Registration (VREG)
Development, deployment and management of Automated Customs Gateway Portal for Import Duty Exemption Certificate (IDEC) and Imported Vehicle identification Number Registration (VREG)
PPP Process: Solicited
| Federal Ministry of Finance, Budget and National Planning | FEC Approval: October 30, 2019 Concession Period: 10 years
| Four Core Technology Solution Ltd. | Under implementation | NGN10 Billion. |
46 | E-Ticketing Solution (Abuja -Kaduna Rail corridor)
Design, Development, Deployment and Management of a Secure Automated Fare Collection (AFC) Solution for the Nigerian Railway Corporation (NRC) Rail Network.
PPP Process: Solicited
| Federal Ministry of Transportation/ Nigerian Railway Corporation | FEC has approved 29th January, 2020 concession period 10 years | Secure ID Nigeria Ltd | Under Implementation | NGN 900,000,000.0 |
47 | The Renovation of Students Hostel
The proposed project is for the rehabilitation of student hostels within Kaduna Polytechnic premises. The hostels will be managed to ensure highest standard of living conditions for the students.
PPP Process: Unsolicited
| Federal Ministry of Education (Kaduna Polytechnic) | FEC Approval: 08 July, 2020
Duration: 19 Years | Mark Point Multilinks Ltd | Under dispute | NGN744,264,000 |
48 | E-Customs Modernization Project
Presidential Initiative to modernize and digitalize the operations of Nigeria Custom Service
PPP Process: Unsolicited
| Nigeria Custom Service (NCS) | FEC Approval: September 20, 2020 | Trade Modernization Project Ltd. | Ratified by FEC: April 19, 2023
Under implementation
| US$3.1 billion
|
49 | Rehabilitation, Expansion and Operation of the Nigerian Correctional Service Shoe, Garment and Leather Factories
Rehabilitation, Expansion and Operation of the Nigerian Prisons Service Shoe Factory (NPS SF) Aba, Abia State under Public Private Partnership between Erojim Investment limited (EIL) and the Nigeria prisons service.
PPP Process: Unsolicited
| Nigeria Correctional Service (NCS) | FEC Approval: 7th Oct 2020 | Messrs. Erojim | Under implementation | US$11,866, ,865
|
50 | Port Harcourt Railway Industrial Park
Development of a Railway Industrial Park in Ubima, Rivers State through PPP arrangements with the following facility components for commercial vehicles and rolling stock assembly, Oil and Gas materials supply Industrial Park, Textile Industrial Park, Light Industry Park for Fast Moving Commodities and Goods (FMCGs).
PPP Process: Solicited | Federal Ministry of Transportation | FEC Approval: 7th Oct 2020 | China Civil Engineering Construction Corporation Ltd. (abbreviation CCECC) | On hold. To be restructured | US$291,253,619 |
51 | Bonny Deep Sea Port
Development of Bonny Deep Water Port through PPP arrangements in order to improve transportation opportunities and boost economic activities along south-south, south-east, north-central and north-east geo-political economic corridors and ease pressure on the western ports – Apapa and Tin Can Island which at the moment handles about 90% of cargo throughput in the country
PPP Process: Solicited | Federal Ministry of Transportation | FEC Approval: 7th Oct 2020 | China Civil Engineering Construction Corporation Ltd. (abbreviation CCECC) | On hold. Dispute over location | US$550,025,361 million |
52 | Ibom Deep Sea Port Project
The development of a Greenfield Deepsea Port and accompanying Free Trade Zone (FTZ) in Akwa Ibom State in the South-South geopolitical zone of Nigeria.
PPP Process: Solicited | Federal Ministry of Transportation (FMoT) Federal Ministry of Transportation / Akwa Ibom State Government
| FEC Approval: December 16 2020 | Bollore/Power China Consortium Bollore Africa Logistics-PowerChina International Group Limited | Yet to achieve commercial close | US$2,016,198 billion |
53 | Police Specialized Services Automation project
The automation of police services to capture revenues accruing to the police through specialized services like VIP coverage etc and remit same to the force.
PPP Process: Unsolicited | Nigeria Police Force | FEC approval on Wednesday 14th July 2021 | Parkway Projects Limited | Under implementation | NGN 2,047,726,450 |
54 | The NAHCON Commercial Development
The Design Finance Build Operate and Transfer of Commercial complex at its landed property located at Hajj Complex, along Katsina Road, Kano State. (The plan is to build a 4blocks complex housing 376 units of shops, 8 portal steel blocks, a mosque, convenience and parking spaces)
PPP Process: Unsolicited
| National Hajj Commission of Nigeria (NAHCON) | FEC approval December 12, 2021 | DID Al-Amana Nigeria Limited | Under implementation | NGN 1812.7 Billion
|
55 | Revenue Assurance Solution (RAS)
Deployment of Revenue Assurance Solution (RAS) to Design, Finance and Implement a solution with the objective of improving Annual Operating Levy (AOL) Revenue computation and collection by the NCC from Network Operators.
PPP Process: Solicited
| Federal Ministry of Communications/Nigeria Communications Commission (NCC) | FEC approval January 26, 2022 concession period 10 years | 3R Revenue Assurance ltd | Under implementation | NGN11.9 Billion |
56 | Onitsha River Port project
The concession Onitsha River Port to improve inland water transportation.
PPP Process: Solicited | Federal Ministry of Transport (FMoT)/ National Inland Waterways Authority (NIWA) | FEC approval February 2, 2022 Concession period 30 years | Universal Elysium Consortium | Under Implementation | NGN 3,935,833,337.0 |
57 | Federal Coastal Fishery Terminal, Ebughu, Akwa Ibom State
Rehabilitation and Operations of the Ebughu Fishery Terminal to provide onshore services to fishing vessels, under water repair and maintenance facilities.
PPP Process: Solicited | Federal Ministry of Agriculture and Rural Development | FEC approval February 16, 2022 concession period 11 years | Messrs Alfin Fisheries Limited | Commercial close achieved | NGN3,685,055,000 |
58 | Redevelopment of K’Maroun Complex in Ijora Lagos State
Redevelopment of the K’Maroun Complex under a PPP arrangement with the following facilities: Office space, Gas powered cold rooms. Lock-up shops and parking spaces.
PPP Process: Unsolicited
| Ogun Osun River Basin Development Authority | FEC Approval April 6, 2022 | Messrs. Asiko International Energy (Nigeria) Limited | Under implementation | NGN 890,000,000.0
|
59 | Badagry Deep-Sea Port, Lagos
Greenfield development designed to cater for containers, dry bulk, liquids, Ro-Ro, oil & gas products, and also operate a free trade and local logistic zones.
PPP Process: Solicited | Federal Ministry of Transportation/ Nigerian Ports Authority | FEC approval August 3, 2022 concession period 45 years | Badagry Port Development Limited. | Under implementation | US$ 2,777,233,000.00 |
60 | Maintenance, Repairs and Overhaul (MRO) Facility
Establishment of an MRO facility for aircraft maintenance, Repairs and supply of parts to the aviation sector
PPP Process: Solicited | Federal Ministry of Aviation | FEC Approval October 12, 2022 | AJW Consortium – AJ Walter and Gloresly Pro-Project | Commercial close achieved | US$ 150,000,000.00 |
61 | Concession of Planetarium and Museum
The project seeks to equip, operate and maintain the Planetarium and Museum at the Obasanjo Space Centre Abuja.
PPP Process: Solicited | National Space Research & Development Agency (NASRDA) | FEC Approval November 2, 2022 | Milky-way Visuals | Awaiting Ministry of Justice clearance | NGN3,593,532,207.00 . |
62 | Satellite broadband Project for rural Nigeria
Research and Development of Satellite Technology and Equipment for the Provision of cost-effective satellite broadband to rural Nigeria
PPP Process: Unsolicited | National Space Research & Development Agency (NASRDA) | FEC Approval November 30, 2022 | Messrs. Gilat Eleo Technology | Awaiting Ministry of Justice clearance | 4,074,371,000.00
|
63 | Nigerian Police DIG Quarters at Maitama District, Abuja
Redevelopment of the Nigerian Police DIG Quarters at Maitama District, Abuja, through Public Private Partnership arrangement
PPP Process: Solicited | Nigeria Police Force | FEC Approval November 30, 2022 | Cosgrove Nigeria | Commercial Close achieved and project commissioned | NGN20,138,230,886
|
64 | FRCN Mixed Use Development of Land in Ikeja
Concession of Six hectares of Land in Ikeja Lagos for Mixed Use Development
PPP Process: Unsolicited | Federal Radio Corporation of Nigeria | FEC Approved on December 21, 2022 for a 55 -year Concession | Fish Valley Nigeria Ltd | Commercial Close achieved | US$200,000,000 |
65 | Western Offshore Waste Reception Facility (OWREF)
Design, Finance, Build, Operate, Maintain and Transfer (DFBOMT) of Western Offshore Waste Reception Facility (OWREF) under a under a PPP arrangement.
PPP Process: Unsolicited | Nigerian Maritime Administration & Safety Agency (NIMASA) | FEC Approval on December 21, 2022 for a 15-year Concession | African Circle Pollution Waste management LTD | Under implementation | US$ 67,042,013 |
66 | Central Offshore Waste Reception Facility (OWREF)
Design, Finance, Build, Operate, Maintain and Transfer (DFBOMT) of Central Offshore Waste Reception Facility (OWREF) under a PPP arrangement.
PPP Process: Unsolicited
| Nigerian Maritime Administration & Safety Agency (NIMASA) | FEC Approval on December 21, 2022 for a 15- year Concession | African Circle Pollution Waste management LTD | Under implementation | US$ 66,590,848 |
67 | Eastern Offshore Waste Reception Facility (OWREF)
Design, Finance, Build, Operate, Maintain and Transfer (DFBOMT) of Eastern Offshore Waste Reception Facility (OWREF) under a PPP arrangement.
PPP Process: Unsolicited
| Nigerian Maritime Administration & Safety Agency (NIMASA) | FEC approval on December 21, 2022 for a15 year Concession Period | XPO Marine Services LIMITED | Under implementation | US$72,164,699 |
68 | NIMASA Modular Floating Dry Dock
The Operations and Maintenance and Transfer of NIMASA floating dry dock, Lagos.
PPP Process: Unsolicited
| Nigerian Maritime Administration & Safety Agency (NIMASA) | FEC approval on December 21, 2022 for a15 year Concession Period | J-Marine Logistics | Yet to achieve Commercial Close | US$19,551,166
(NGN 8,113,733,890). |
69 | Refurbishment of Water System at Apapa Port
To Refurbish an complete the water system at the Apapa Port to ensure adequate water supply to vessels
PPP Process: Unsolicited
| Federal Ministry of Transportation (FMOT)/ Nigeria Ports Authority | 16 year Concession Period | Tecnis EPC International limited Nigeria | Yet to achieve Commercial Close | 5.8542Billion Naira |
70 | Highway Development and Management Initiative (HDMI)
The Construction & Maintenance of 12 corridors under a highway development and management initiative (HDMI): Route 1: Benin- Asaba 125 km road
PPP Process: Solicited
| Federal Ministry of Transportation (FMOT) | FEC approval on January 19, 2023 for a 25-year Concession Period | Africa Plus consortium | Commercial Close achieved | NGN 87,258,586,463 (US$189,692,579) |
71 | Highway Development and Management Initiative (HDMI)
The Construction & Maintenance of 12 corridors under a highway development and management initiative (HDMI): Route 2: Abuja - lokoja 195km road
PPP Process: Solicited
| Federal Ministry of Transportation (FMOT) | FEC approval on January 19, 2023 for a 25-year Concession Period | Avia Infrastructure Services Limited AISL | Commercial Close achieved | NGN 134,006,560,000
(US$291,318,609) |
72 | Highway Development and Management Initiative (HDMI)
The Construction & Maintenance of 12 corridors under a highway development and management initiative (HDMI): Route 4: Onitsha - Owerri - Aba 161.2 km road
PPP Process: Solicited
| Federal Ministry of Transportation (FMOT) | FEC approval on January 19, 2023 for a 25-year Concession Period | Eyimba Economic City Consortium | Commercial Close achieved | NGN 104,410,351,000
(US$226,979,023) |
73 | Highway Development and Management Initiative (HDMI)
The Construction & Maintenance of 12 corridors under a highway development and management initiative (HDMI): Route 5: Shagamu - Benin 258km road
PPP Process: Solicited
| Federal Ministry of Transportation (FMOT) | FEC approval on January 19, 2023 for a 25-year Concession Period | AFC/Mota Engil Consortium | Commercial Close achieved | NGN 122,271,257,000
(US$265,807,080) |
74 | Highway Development and Management Initiative (HDMI)
The Construction & Maintenance of 12 corridors under a highway development and management initiative (HDMI): Route 6: Abuja-keffi-Akwanga 175.9km road
PPP Process: Solicited
| Federal Ministry of Transportation (FMOT) | FEC approval on January 19, 2023 for a 25-year Concession Period | China Harbour Engineering Company ltd CHEC | Commercial Close achieved | NGN 3,028,612,000
(US$6,583,939) |
75 | Highway Development and Management Initiative (HDMI)
The Construction & Maintenance of 12 corridors under a highway development and management initiative (HDMI): Route 7A: Kano – Shuari 100km road
PPP Process: Solicited
| Federal Ministry of Transportation (FMOT) | FEC approval on January 19, 2023 for a 27-year Concession Period | Dafac Consortium | Commercial Close achieved | NGN 39,135,027,712
(US$85,076,147) |
76 | Highway Development and Management Initiative (HDMI)
The Construction & Maintenance of 12 corridors under a highway development and management initiative (HDMI): Route 9: Enugu – Port Harcourt 200km road
PPP Process: Solicited
| Federal Ministry of Transportation (FMOT) | FEC approval on January 19, 2023 for a 25-year Concession Period | Eyimba Economic City Consortium | Commercial Close achieved | NGN 157,967,789,000
(US$343,408,237) |
77 | Highway Development and Management Initiative (HDMI)
The Construction & Maintenance of 12 corridors under a highway development and management initiative (HDMI): Route 11: Lagos – Ota – Abeokuta 80km road
PPP Process: Solicited
| Federal Ministry of Transportation (FMOT) | FEC approval on January 19, 2023 for a 25-year Concession Period | Africa Plus consortium | Commercial Close achieved | NGN 84,456,920,908
(US$183,602,002) |
78 | Highway Development and Management Initiative (HDMI)
The Construction & Maintenance of 12 corridors under a highway development and management initiative (HDMI): Route 12: Lagos – Badagry – Seme Border 79km road
PPP Process: Solicited
| Federal Ministry of Transportation (FMOT) | FEC approval on January 19, 2023 for a 25-year Concession Period | AFC/Mota Engil Consortium | Commercial Close achieved | NGN 54,175,434,000
(US$117,772,683) |
79 | Refurbishment of Water System at TinCan Island Port
To Refurbish an complete the water system at the Tin can Island Port to ensure adequate water supply to vessels
PPP Process: Unsolicited
| Federal Ministry of Transportation (FMOT)/ Nigeria Ports Authority | 16-year Concession Period | Sandust Energy and Engineering Services Limited | Yet to achieve Commercial Close | 4.658 Billion Naira |
80 | Cassava Bio-mass, Bio-ethanol Value Chain
The conversion of Cassava to Bio ethanol and to harness the value chain along the process.
PPP Process: Unsolicited
| Federal Ministry of Finance Budget & National Planning | Approved: April 19, 2023 Concession Period: 5 Years | Bio Sources and Technologies ltd | Commercial close achieved | 11.9bn
|
81 | National Fire Detection and Alarm System (NAFDAS)
The Federal Ministry of Interior through the Federal Fire Service submitted an unsolicited proposal for a cloud-based system PPP project. This project is designed and deployed to address the shortcomings in information sharing between Fire Alarm Detection Notification and Control Systems, System Administrator, and Fire Service for improved Risk Management through real time analysis and prompt action.
PPP Process: Unsolicited
| Federal Ministry of Interior/Federal Fire Service (FFS) | FEC approval the FBC on April 19, 2023 for 15-year Concession Period | Hoist Life Safety Systems | Yet to achieve commercial close | NGN 3,500,000,000 |
82 | Digitalization of the Fund-wide activities/processes and automation of employee contribution & compensation scheme of the NSITF (E-NSITF (Phase -2))
This is an integrated Business Management Solution that is designed to digitally transform the organizations operations by providing a consolidated and unified data/information repository targeted at increasing efficiency, agility and output in the daily operations of the NSITF through superior tracking and reporting, database management and data sharing and overall improved information systems.
PPP Process: Unsolicited
| Federal Ministry of Labour & Employment/ NSITF | FEC approval the FBC on April 19, 2023 for 15-year Concession Period | P2E Technologies | Commercial Close achieved | NGN 15,000,000,000 |
83 | Lagos-Ibadan Rail E-Ticketing Concession
Design, Development, Deployment and Management of a Secure Automated Fare Collection (AFC) Solution for the Nigerian Railway Corporation (NRC) Rail Network.
PPP Process: Solicited
| Nigeria Railway Corporation | Approved: May 10, 2023 | Global software digital solutions ltd/Datamatics Global Services ltd consortium | Awaiting commercial close | NGN 1,100,000,000 |
84 | Warri-Itakpe Rail E-Ticketing Concession
Design, Development, Deployment and Management of a Secure Automated Fare Collection (AFC) Solution for the Nigerian Railway Corporation (NRC) Rail Network.
PPP Process: Solicited
| Nigeria Railway Corporation | Approved: May 10, 2023 | Fane International Consult ltd/ Artificial Intelligence Technologies ltd Consortium | Awaiting commercial close | NGN 860,806,423
|
85 | Device Management System
The design, financing, operations, maintenance and transfer of a central remote management system to address the proliferation of fake, counterfeit, substandard, and cloned ICT devices in the telecommunications industry in Nigeria.
PPP Process: Solicited
| Nigeria Communication Commission | Approved: May 10, 2023 | Messrs. Inmobile Holdings SAL and Grand Inmobiles Nigeria ltd | Commercial Close to be achieved. | US$26 million |
86 | 40mw Kashimbilla Hydropower (HPP) Project
Operations and Maintenance of the 40MW Kashimbilla HPP located on the Katsina Ala River in Takum LGA, Taraba State.
PPP Process: Solicited
| Federal Ministry of Water Resources | Approved: May 10, 2023 | Messrs. Mainstream Energy Solutions Ltd. | Commercial Close to be achieved. | NGN 7,680,000,000 |
87 | 360mw Gurara II Multipurpose Dam Project
A greenfield project for the Operation, Maintenance and Transfer of the 360MW HPP plant in Gurara II, on the Gurara River, in Niger State.
PPP Process: Solicited
| Federal Ministry of Water Resources | Approved: May 10, 2023 | Messrs. CGCOC Group Co. Ltd. | Commercial Close to be achieved. | US$ 1.123billion
NGN 485,310,631,000 |
88 | Electronic Civil Registration and Vital Statistics System (eCRVS) Platform
Development of an Electronic Civil Registration and Vital Statistics (eCRVS) through the use of a robust high-end technology structure to capture real time, quality, reliable and verifiable statistics on births, deaths, marriages and divorce and to contribute to the nation’s revenue generation through the registration of vital statistics in the country.
PPP Process: Unsolicited
| National Population Commission | Approved 15 (Special Monday FEC) | Messrs Barnksforte Technology Limited | Awaiting commercial close | NGN 5.3billion |
89 | Aviation Leasing Company
The establishment of ALC to alleviate the problem of aircraft leasing and high insurance premium charges to Nigerian Airlines on Aircraft leasing
PPP Process: solicited
| Federal Ministry of Aviation | Approved May 15, 2023 | Messrs AJW Consortium | Awaiting commercial close | US$35,000,000 |
90 | The Rehabilitation and Expansion of the Burutu Port Burutu Port is located in Burutu Local Government Area of Delta State. The current Port is on a 40.716 Hectares of Land and was originally built as a logistic Port for the export of Solid minerals and Agricultural Produce as well as importation and transportation of foreign goods from Europe for onward movement to the hinterland River Ports via the inland waterway.
PPP Process: Unsolicited
| Federal Ministry of Transport/Nigerian Ports Authority
|
FEC approval the FBC on May 17, 2023 for 40-year Concession Period | Akewa Colmar Terminal Limited (ACTL) | Awaiting commercial close | US$ 1.28 billion |
91 | Port of Ondo Multipurpose Deep-Sea Port
The Port of Ondo is planned to be developed as a greenfield project that aims to serve as a multi-purpose deep seaport. Located along the coast of Ondo State, the port when completed will create one of the most modern ports in Nigeria, with the largest solid minerals terminal located contiguous to an Industrial City with Free Trade Zone (FTZ) status.
PPP Process: Solicited
| Federal Ministry of Transport/Nigerian Ports Authority | FEC approval the FBC on May 17, 2023 for 50-year Concession Period | China Railway Eryuan Engineering Group Co. Ltd (CREEC) | Awaiting commercial close | US$1.4Billion |
92 | The Expansion and development of Snake Island Multipurpose Sea Port
The proposed Snake Island Terminal is envisioned to be developed as a green port, comprising of 3 terminals with 2.5km of quay, 6 ship berths, 9 barge berths, 6.0 to 16.0 meters of draft and an overall area of 85 hectares.
PPP Process: Unsolicited
| Federal Ministry of Transport/Nigerian Ports Authority | FEC approval the FBC on May 17, 2023 for 45-year Concession Period | Nigerdock and Snake Island Integrated Free Zone |
Awaiting commercial close | US$ 974.19 mil |
93 | On street park and pay in the FCT
The project is a regularization project for the operations and management of an on-street park and pay services to be deployed in Abuja Municipality. The FCT has been divided into several zones to be managed by different operators/concessionaires
PPP Process: Unsolicited
| Abuja Infrastructure Investment Centre
| FEC approval the FBC on May 17, 2023 | -Automen Technik Bauman Nig Ltd -Najec Ltd | Awaiting commercial close | NGN 475 million (Zone A)
NGN433.3 mil (Zone B) |
94 | Expatriate Employment Levy
A project that will place a levy on offshore earnings of expatriates to increase non-oil revenue and support for Nigeria
PPP Process: Unsolicited
| Federal Ministry of Finance, Budget & National Planning (FMBNP) | FEC approval the FBC on May 17, 2023 for 20-year Concession Period | Air Wave Limited | Awaiting commercial close | US$ 95,024,000 |
95 | Concession of Mallam Aminu Kano International Airport, Kano
The FGN proposed to concession the Murtala Muhammed International Airport Terminal Building, Lagos State as part of aviation sector reform programme to Rehabilitate/Build – Operate and Transfer
PPP Process: solicited
| Federal Ministry of Aviation
| FEC approval the FBC on May 17, 2023 for 30-year Concession Period | Corporation America Airports S.A, Mota Engil (CAAP) | Awaiting commercial close | US$ 86 million, |
96 | Concession of Nnamdi Azikiwe International Airport, Abuja
The FGN proposed to concession the Nnamdi Azikiwe International Airport Terminal as part of aviation sector reform programme to Rehabilitate/Build – Operate and Transfer
PPP Process: solicited | Federal Ministry of Aviation
| FEC approval the FBC on May 17, 2023 for 20-year Concession Period | Corporation America Airports S.A, Mota Engil (CAAP) | Awaiting commercial close | US$17.48 million |
97 | Development of Senior Police officer’s quarters at Ikeja, Lagos The redevelopment of 6.75 hectare of land at Ikeja into senior police officer’s housing units using 2.1 hectares of the land and use of 4.65 hectares for the development of 130 four-bedroom duplex housing units.
PPP Process: Unsolicited | Nigeria Police | FEC approval the FBC on May 17, 2023 for 50-year Concession Period | Black Qoral Concepts ltd | Awaiting commercial close | NGN 7.4 billion |
98 | Regularization Process: Editorial Services and Publication of the Laws of the Federation of Nigeria and All Nigeria Law Report
PPP Process: Unsolicited
| Federal Ministry of Justice | FEC approval the FBC on May 23, 2023 for 15-year Concession Period | LexisNexis legal and professional ltd. | Awaiting commercial close | NGN 105.5 million |
99 | Publishing and Marketing of Court Appeal (specialized) Law Report
PPP Process: Unsolicited
| Federal Ministry of Justice | FEC approval the FBC on May 23, 2023 for 15-year Concession Period | Jafrex Integrated services | Awaiting commercial close | |
100 | NIWA Business Processes (E-NIWA)
The Deployment and digitalization and automation of NIWA processes and activities
PPP Process: Unsolicited
| Federal Ministry of Transport (FMoT)/ National Inland Waterways Authority (NIWA) | Approved May 23, 2023
30 years | P2E Technologies Limited | Awaiting commercial close | NGN 7 billion |
101 | Electronic E-Call Up System at Onne Port
Implementation of the Electronic Truck Call Up system aimed at increasing cargo/truck traffic at Onne Port.
PPP Process: Unsolicited
| Nigeria Ports Authority | Approved May 23, 2023 15-years | Forge Concepts | Awaiting commercial close | NGN 1.5 billion |
102 | 700 MW Zungeru Hydro Electric Power Plant
The project is a solicited project initiated by BPE/FMOP for the concession of the operation and maintenance of the hydropower asset.
PPP Process: Solicited | Federal Ministry of Power (FMoP)/FMoWR/ Bureau of Public Enterprises (BPE) | FEC Noted the NCP approval of the FBC on May 23, 2023 for 25-year Concession Period | Mainstream Energy | Awaiting Ministry of Justice clearance | US$ 1.2 billion |
103 | Concession of the Central Workshop Ijora
The rehabilitation and optimal operation of the facility to manufacture, maintain and provide engineering services through a Rehabilitate-Operate-Maintain-Transfer PPP model.
PPP Process: Unsolicited
| Federal Ministry of Works | Approved October 19, 2023 | Beta Transport Nigeria limited | Awaiting commercial close | NGN888.1m |